Since March I have been sending emails to the Planning Department about 2 omissions from the Development Plan.  I got no replies so I had to raise this by question at the monthly Council meeting.  Although the question was submitted 2 weeks ago, the website versions of the plans still as of today have not been changed.
FINGAL COUNTY COUNCIL MEETING

MONDAY 9th OCTOBER, 2006

ITEM NO.  7

AMENDMENT OF GB02 AND CYCLE ROUTE OBJECTIVE AT CLAREMOUNT ROAD IN DEVELOPMENT PLAN

Question:    Councillor D. Healy
“To ask the Manager what steps have been taken to correct the following errors in the printed and website versions of the Development Plan since the errors were brought to the attention of the Planning Department in March
The omission of the text “within 2 years” at the end of Objective GB02 as amended at the meeting of 30/05/2005
The omission of the cycle route objective between Claremount Road and claremount level crossing.”

Reply:
It would not be practical or feasible to run entire reprints of the Development Plan to correct these errors.  As a result, erratum slips will be prepared for insertion into the printed versions of the Development Plan.  The Drawing Office is currently working with the IT Department to upgrade the layout of the website and the quality of the maps displayed on the site.  It is intended to correct the errors outlined by the Councillor as part of this wider process.